    3/23/18 – Framing is underway for the new classroom building, and the center slab has been poured. The school’s new circular drive is also starting to take shape.


    Construction Timeline:

    December 2017 – Shovels in, fences up! Ground work
    January 2018 – Vertical construction begins
    Summer 2018 – New buildings open to students and staff

    Pima Project Photos


    Timelapse Video

    Please note, this camera is faced away from the current school buildings and will not show any children - only construction crews.
    Watch a timelapse of the Pima Traditional construction.


    Pima Documents & Links

    Floorplans for the Admin and Multipurpose buildings are currently under review.

    Classroom Building Floorplan
    • PNG Download (Updated 9/2/2017)
    Exterior Design
    • Exterior Design 1 (Updated 9/5/2017)
    • Exterior Design 2 (Updated 9/5/2017)
    • Exterior Design 3 (Updated 9/5/2017)
    • Exterior Design 4 (Updated 9/5/2017)
    Construction Phases
    • PDF Download (Updated 12/8/2017)
    Interior Classroom Windows
    • PDF Download (Updated 9/18/2017)
    Administrative Building Floorplan
    • JPG Download (Updated 10/6/2017)
    Multi-purpose Building Floorplan
    • JPG Download (Updated 10/6/2017)
    Site Plan
    • JPG Download (Updated 10/6/2017)


    Project Photo Gallery (select this link)


    Rebuild Committee Members

    Thank you very much to the parents and staff members who signed up to be part of this exciting process. The committee will represent the community in providing input on the design of the new campus.

    Lead:
    Alexis Cruz-Freeman - Principal

    Committee Members:
    Damien Mendoza - Parent
    Josh Friedman - Parent & PTO President
    John Selkirk - Teacher
    Colleen Felix - Teacher
    Janet Navarro - Teacher
    Kimberly Mills - Assistant Principal
    Paul Thomas - Facilities Coordinator
    Dan Bentel - Parent
    Melissa Willis - Parent